Latest Blog Entries:
Add to Google
05/12/08 - Week Eight, Two Months and More than Two Miles of Shoreline Completed!







The end of last week saw the project moving beyond Barrier Dunes toward the Shoreline Drive area. Work is concentrating now on filling the beach to the north of Shoreline Drive. To help people understand how the project moves down the beach, a quick discussion of what are called "sub lines" may be useful. Three submerged lines are placed at strategic points along the shoreline. Typically when construction begins from a new sub line, work will be directed to the north of that line for approximately 2,000 feet. Once the beach is filled as far northward as required, the pumping turns to the south of that line for another approximate 2,000 feet. When that southern 2,000 or so feet are completed, the work "jumps" to the next submerged line to the south. Occasionally conditions will require work to be conducted outside this typical pattern, but this gives you a basic idea of what to expect. The biggest movement of the project, pipe, and equipment occurs when first jumping south to a new sub line -- for example, from north of Barrier Dunes to Shoreline Drive.

We wanted to revisit the subject of sand fencing and stairs. As much as we had hoped to be able to provide property-by-property assessments, the time and manpower required is just not always available. Please remove ALL SAND FENCING from the dunes. If your steps extend beyond the vegetation line, you should consider removing the portion that is out onto the sandy beach. In some cases, just removing the railings will be enough. If you have specific questions about vendors or your particular property, email us at info@savethecape.com and we’ll do our best to assist. Also, there are representative examples in the photo gallery called "First Segment Walkovers, Stairs & Fencing Recommendations" that you may find useful in deciding what to do with your walkovers.

Finally we want to discuss the planned, natural phenomenon that our completed beach will experience: equilibration.    A certain amount of the sand that's placed on the beach is intended to migrate back into the water and rebuild the sandbar system and underwater toe of the dune. This migration, or equilibration, can occur over a period of months or years, depending on the weather events taking place. With the unseasonably rough weather we’ve experienced in May so far, some equilibration is probably beginning to take place. In some beach projects, residents and visitors were concerned to see some of the sand leaving the shore. We want to assure you that as this process takes place, it's doing exactly what it's supposed to, and the migration of that sand was incorporated as part of the beach design.

Finally, the new photo gallery that will be added to the website sometime today contains pictures from May 7-9. These were taken in and around Sea Cliffs, Barrier Dunes and Shoreline Drive. Our pictures with today's blog include some of these photos. The first photo is a shot of the completed beach in front of Sea Cliffs and Barrier Dunes. The second shot shows the new Shoreline Drive submerged line being placed. The third shot shows a lot of action -- the dredge is in the background, the fill shack is being moved down the beach to the south, the survey crew is working on the shoreline, and you can also see the diverter, where the flow of sand between the two pipes on the beach is controlled.


Reply Posted: 05/12/08 Thanks for the lesson on sub-lines.

Q. How many times has the sub-line been moved so far and how long has it been taking between moves. Thanks!

- Anne


Reply Posted: 05/12/08 Many thanks to Laurel, Susan, Paula and everyone who has worked so hard on this project! I also appreciate all of the updates and photos! I visit the Cape several times each year and knew the first visit that my heart had been forever captured! I can't wait to visualize the progres and have the new sand between my toes! Thanks again to all who have made this a reality!
Tamara

- Tamara Currier

Reply Posted: 05/12/08 Thanks for the pics. Its nice to be able to keep up with whats happening around my winter home

- Gene Hein

Reply Posted: 05/12/08 Hi, Anne! Those are good questions. I am not positive, but I think the jump to Shorline Drive is the fourth subline. Michael can jump in and correct me if I'm wrong!

As far as how long it takes between moves, I think that has been variable. Again, Michael can correct me if there's a definite average thus far. (But of course the averages from the north end of the project will probably be vastly different than the middle or southern end because the amount of fill continues to increase as you move to the south).



- Laurel Eiler, SJPBAC Co-Chair


Reply Posted: 05/13/08 Hello Again Folks!
I don’t want to be a pest; with my questions…here is one more:
Q/: will home owners be allowed to place sand fence on the newly built berm before the vegetation is planted by the contractor or?
Thanks
Richard and Jacky "Paradiso"


- Richard & Jacky

Reply Posted: 05/13/08 Paradiso:

Yes, As long as it is done after turtle season and in compliance with FWC standards and quidelines.

- Paula Ramsey Pickett, TDC Director




Post Reply




With great appreciation, portions of this site were used with permission from the Florida DEP, the City of Destin, the Town of Hilton Head Island and Sand Key.

The content provided herein is for informational purposes only and does not necessarily reflect the views or opinions of the Gulf County Tourist Development Council or Gulf County, Florida.

©2005-2008, Bluewater iNet Group, LLC
St. Joseph Peninsula Beach Advisory Committee